| Treatment no.: | 4.3.3.6 |
| ID no.: | 4.3.3.6 |
| Position: | Platform |
| Size: | L990mm x W580mm x H280mm |
| Damage Condition: | Fragment, Scaling |
| Repair case: | 5a |
| Treatment | |
| Specification: | Epoxy adhesive (B7 = 7.5ml) + (Sandstone Powder = 15g) |
| Injection: Polymer( P-2e =80g) + Cement (C-2 = 100g) | |
| Gap filling by: Polymer P-1c + Water + Cement + Sand + Metyl Cellulose | |
| Date of start: | 21 Mar 2008 |
| Date of finish: | 28 Mar 2008 |
| Person in charge: | Khieu Mony & Cheam Pross |
| Photograph Before Treatment | Photograph After Treatment |
![]() |
![]() |
| North face | North face |
![]() |
![]() |
| South face | South face |
![]() |
![]() |
| East face | East face |
![]() |
![]() |
| West face | West face |
![]() |
![]() |
| Top | Top |
![]() |
![]() |
| Bottom | Bottom |
![]() |
![]() |
| Oblique | Oblique |
![]() |
![]() |
| Oblique | Oblique |
![]() |