| Treatment no.: | 3.4.5.5 |
| ID no.: | 3.4.5.5 |
| Position: | Pilaster |
| Size: | L940mm x W400mm x H245mm |
| Damage Condition: | Fissure |
| Repair case: | 5a |
| Treatment | |
| Specification: | Injection: Polymer( P-2e =303g) + Cement (C-2 = 350g) |
| Gap filling by: Polymer P-1c + Water + Cement + Sand + Metyl Cellulose | |
| Date of start: | 16 Jul 2007 |
| Date of finish: | 23 Jul 2007 |
| Person in charge: | Khieu Mony & Cheam Pross |