Treatment no.: | 2.2.8.39 |
ID no.: | 2.2.8.39 |
Position: | Platform |
Size: | L570mm x W490mm x H250mm |
Damage Condition: | Fragment, Flaking |
Repair case: | 1+5a |
Treatment | |
Specification: | Epoxy adhesive (B7 = 15ml) + (Sandstone Powder = 30g) |
Injection: Polymer( P-2e =152g) + Cement (C-2 = 220g) | |
Gap filling by: Polymer P-1c + Water + Cement + Sand + Metyl Cellulose | |
Date of start: | 08 May 2008 |
Date of finish: | 26 May 2008 |
Person in charge: | Khieu Mony & Cheam Pross |
Photograph Before Treatment | Photograph After Treatment |
North face | North face |
South face | South face |
East face | East face |
West face | West face |
Top | Top |
Bottom | Bottom |
Oblique | Oblique |
Oblique | Oblique |